Sucati Dam and HEPP Project Timeline

Energy

Telecom

Defense

Air Traffic Control

Construction

 

Turkce

ERE Home

Quality Policy

About ERE

ERE Companies

White papers by ERE on the Turkish national energy policy are available in our publications page.

Sucati

Sucati

Sucati

Sucati

A framework agreement towards the Sucati Dam and HEPP was reached between ERE and the Turkish Ministry of Energy and Natural Resources following technical, administrative and financial discussions and ratified by the Turkish Supreme Court in 1996. A Concession Agreement was signed between ERE and the Ministry on May 31 of that year.

Site installations were completed and construction activities started in June 1998. Although feasibility studies suggested a three year time frame for the construction work, ERE was able to complete the project in twenty months, thanks to effective project management, the use of the latest engineering applications and the highest possible performance by all personnel involved.

Sucati Dam and HEPP installations performed excellently during test runs on January 17 and 18, 2000 before the representatives of

·  the owner, Republic of Turkey, Ministry of Energy and Natural Resources

·  the investor, ERE Electricity Company,

·  the civil works contractor, ERE Engineering Company and

·  the electromechanical works contractor, Siemens AG, Austria

Commercial operation began on January 18, 2000 after Preliminary Acceptance by the Ministry, which gave its Final Acceptance on February 27, 2001.