Penstock
and Power House Excavation
Settling
Pond Interior
Settling
Pond Entrance (view from T1 exit)
View
of Settling Pond From Inside T2
T2
Tunnel (3,140.71m in total) was completed when excavation from Head:3
(1,365.14m) and Head:4 (1,775.57m) met on 21.12.2002, at 07:30 hours.
Site
Team and Management Staff at the Meeting Point of Simultaneous
Excavations (from Entrance:3 and Entrance:4) of T2 Tunnel
|