ERE Holding Headquarters

DAGPAZARI Project, Dec'01 - Jun'02

Energy

Telecom

Defense

Air Traffic Control

Construction

 

Turkce

ERE Home

Quality Policy

About ERE

ERE Companies

 

Sucati

Sucati

Sucati

Sucati


Open channel - completed section (May 2002)


Open channel - concrete walls (April 2002)


Tunelling works (April 2002)


T1 exit (April 2002)


T2 exit (April 2002)


Open channel - bottom slab (March 2002)


Tunnel lining (steel supports + shotcrete) (March 2002)


Open channel - T2 exit (March 2002)


T2 entrance (March 2002)


T1 entrance (March 2002)


T2 exit (February 2002)


T1 exit and acces road excavation (February 2002)


T1 exit (December 2001)


T1-T2 channel - excavation (December 2001)


Open channel - excavation (December 2001)

 